1
00:00:36.000 --> 00:00:40.000
When it comes to building skyscrapers, there
is no piece of construction equipment more

2
00:00:40.000 --> 00:00:42.000
essential than the tower crane.

3
00:00:42.000 --> 00:00:47.000
These heavy lifting machines dominate city
skylines, hoisting materials and machinery

4
00:00:47.000 --> 00:00:50.000
to some of the highest construction sites
on Earth.

5
00:00:50.000 --> 00:00:55.000
They have become a part everyday life in almost
every major city as contractors race to build

6
00:00:55.000 --> 00:01:00.000
high-rise after high-rise, and more than 100,000
can be found in operation around the world

7
00:01:00.000 --> 00:01:02.000
at any given time.

8
00:01:02.000 --> 00:01:07.000
Despite how common tower cranes are, they
often seem to appear in the sky out of nowhere

9
00:01:07.000 --> 00:01:10.000
leaving many of us wondering how they got
there in the first place.

10
00:01:10.000 --> 00:01:15.000
The vast majority are erected using mobile
cranes that are larger in size, but obviously

11
00:01:15.000 --> 00:01:19.000
this cannot always be done when you are building
a record-breaking structure and taller cranes

12
00:01:19.000 --> 00:01:21.000
simply don’t exist.

13
00:01:21.000 --> 00:01:25.000
Some construction sites in dense urban areas
may not have enough space for a large mobile

14
00:01:25.000 --> 00:01:31.000
crane either, and many projects also require
tower cranes to be erected in stages so that

15
00:01:31.000 --> 00:01:34.000
they rise in unison with the constructed portion
of the building.

16
00:01:34.000 --> 00:01:38.000
In these scenarios, the cranes must raise
themselves to the final working height all

17
00:01:38.000 --> 00:01:42.000
on their own using a method known as climbing,
and that is what we will be looking at in

18
00:01:42.000 --> 00:01:43.000
today’s video.

19
00:01:43.000 --> 00:01:49.000
In general terms, climbing a tower crane simply
refers to the process of adding or removing

20
00:01:49.000 --> 00:01:53.000
sections of the mast in order to increase
or decrease the overall height.

21
00:01:53.000 --> 00:01:58.000
The concept is fairly straightforward in principle,
but it is quite difficult to execute safely

22
00:01:58.000 --> 00:02:03.000
in the field with catastrophic consequences
if anything should go wrong.

23
00:02:03.000 --> 00:02:07.000
It is one of the most dangerous operations
that can be performed with a tower crane,

24
00:02:07.000 --> 00:02:11.000
and it is only carried out when absolutely
necessary to complete a project.

25
00:02:11.000 --> 00:02:16.000
Before climbing can begin, a tower crane must
first be erected to an initial height using

26
00:02:16.000 --> 00:02:18.000
a suitable mobile crane.

27
00:02:18.000 --> 00:02:22.000
The process begins by constructing a stable
foundation, which usually consists of a large

28
00:02:22.000 --> 00:02:27.000
concrete slab reinforced with steel rebar,
and this takes place about a month before

29
00:02:27.000 --> 00:02:31.000
the crane goes vertical so that the concrete
has enough time to cure.

30
00:02:31.000 --> 00:02:35.000
Once the concrete has reached its full strength,
the first steel truss section of the mast

31
00:02:35.000 --> 00:02:41.000
is lifted into place, and it is secured with
anchor bolts that are embedded in the foundation.

32
00:02:41.000 --> 00:02:44.000
Additional sections are then stacked on top
of one another to complete the tower portion

33
00:02:44.000 --> 00:02:49.000
of the crane, and they are fastened together
with high-strength steel bolts.

34
00:02:49.000 --> 00:02:53.000
The mast is topped off with a slewing unit,
which is basically a turntable that allows

35
00:02:53.000 --> 00:02:58.000
the top of the crane to rotate, and this serves
as a base for the operator’s cab and lifting

36
00:02:58.000 --> 00:02:59.000
components.

37
00:02:59.000 --> 00:03:03.000
The exact arrangement of the top assembly
varies depending on the type of tower crane,

38
00:03:03.000 --> 00:03:08.000
but the one shown here has a hammerhead configuration
with a cathead and a fixed jib that cannot

39
00:03:08.000 --> 00:03:10.000
be moved up or down.

40
00:03:10.000 --> 00:03:14.000
The cathead is the first component to be installed
on top of the slewing unit, followed by the

41
00:03:14.000 --> 00:03:19.000
counter jib and working jib, and these are
connected with steel tie rods that help to

42
00:03:19.000 --> 00:03:21.000
transfer loads to the mast.

43
00:03:21.000 --> 00:03:26.000
Once the top assembly is complete, a counterweight
is then added to the counter jib, which normally

44
00:03:26.000 --> 00:03:29.000
consists of several concrete slabs.

45
00:03:29.000 --> 00:03:34.000
The counterweight helps to balance the load
when the crane is performing a lift, effectively

46
00:03:34.000 --> 00:03:39.000
reducing the bending moment, or torque, that
must be carried by the mast.

47
00:03:39.000 --> 00:03:44.000
Since the working jib is fixed on this particular
crane, a trolley system must be used to adjust

48
00:03:44.000 --> 00:03:49.000
the radius of the hook so that the load can
be positioned closer or further from the mast.

49
00:03:49.000 --> 00:03:54.000
This is not the case for luffing jib tower
cranes, however, as they can adjust the radius

50
00:03:54.000 --> 00:03:57.000
simply by raising or lowering the working
jib.

51
00:03:57.000 --> 00:04:01.000
In either case, the ability to change the
position of the load makes it possible to

52
00:04:01.000 --> 00:04:06.000
perfectly balance the crane on top of the
mast, and this is essential for the climbing

53
00:04:06.000 --> 00:04:08.000
process to be carried out safely.

54
00:04:08.000 --> 00:04:12.000
When a tower crane is ready to be climbed,
a steel climbing frame is first assembled

55
00:04:12.000 --> 00:04:17.000
around the base of the tower, and it is lifted
up to the underside of the slewing unit.

56
00:04:17.000 --> 00:04:21.000
The frame has a square cross-section with
a lattice structure around three sides, but

57
00:04:21.000 --> 00:04:25.000
the front is left open so that new mast sections
can pass through.

58
00:04:25.000 --> 00:04:30.000
The top is securely fastened to the underside
of the slewing unit with high-strength steel

59
00:04:30.000 --> 00:04:34.000
bolts, and a hydraulic jack at the bottom
is positioned over a push point on the existing

60
00:04:34.000 --> 00:04:35.000
mast.

61
00:04:35.000 --> 00:04:39.000
A new mast section is then hoisted up to the
frame, where it is either placed on a steel

62
00:04:39.000 --> 00:04:44.000
tray or suspended from a guide rail that extends
out above the opening.

63
00:04:44.000 --> 00:04:48.000
At this point, the top of the crane must be
perfectly balanced over the jack before it

64
00:04:48.000 --> 00:04:53.000
can be lifted, which is accomplished by placing
a weight on the hook to offset the counterweights.

65
00:04:53.000 --> 00:04:58.000
An additional mast section is typically used
for this, and it is positioned at a precise

66
00:04:58.000 --> 00:05:03.000
radius from the mast so that there is no net
moment applied onto the climbing frame.

67
00:05:03.000 --> 00:05:07.000
The crane top essentially behaves like a large
balance scale during the climb, and it could

68
00:05:07.000 --> 00:05:11.000
topple off the mast if its center of gravity
is not in line with the jack.

69
00:05:11.000 --> 00:05:16.000
In addition, the climbing frame is not designed
to carry significant torsion, and it is extremely

70
00:05:16.000 --> 00:05:20.000
important that the crane is not slewed during
the climbing process.

71
00:05:20.000 --> 00:05:24.000
The new mast sections are therefore arranged
in a straight line on the ground to eliminate

72
00:05:24.000 --> 00:05:29.000
any need to rotate the crane, and the operator
will usually leave the cabin during the climb

73
00:05:29.000 --> 00:05:32.000
so that the crane cannot be slewed accidentally.

74
00:05:32.000 --> 00:05:36.000
Once the crane is confirmed to be in balance
and all safety checks have cleared, the hydraulic

75
00:05:36.000 --> 00:05:40.000
cylinder is then pressurized to take the weight
of the crane top, and the slewing unit is

76
00:05:40.000 --> 00:05:43.000
unbolted from the top of the mast.

77
00:05:43.000 --> 00:05:47.000
The cylinder is used to lift the climbing
frame along with the top of the crane until

78
00:05:47.000 --> 00:05:51.000
there is enough clearance to insert a new
mast section, which usually requires several

79
00:05:51.000 --> 00:05:54.000
strokes depending on the cylinder’s length.

80
00:05:54.000 --> 00:05:58.000
The mast section can then be maneuvered inside
the frame, where it is bolted to the underside

81
00:05:58.000 --> 00:06:03.000
of the slewing unit, and the hydraulic cylinder
is depressurized so that the bottom of the

82
00:06:03.000 --> 00:06:06.000
new section engages with the top of the existing
mast.

83
00:06:06.000 --> 00:06:11.000
After the joints are securely fastened, the
cylinder is retracted and repositioned on

84
00:06:11.000 --> 00:06:17.000
the next push point, and the whole cycle can
repeat until the crane reaches the desired height.

85
00:06:39.000 --> 00:06:43.000
Once the process is complete, the climbing
frame will either be lowered down the mast

86
00:06:43.000 --> 00:06:48.000
or removed entirely until it is needed to
raise the crane higher or to bring it back

87
00:06:48.000 --> 00:06:50.000
down at the end of construction.

88
00:06:50.000 --> 00:06:55.000
Now, up to this point, we have only talked
about tower cranes that climb externally on

89
00:06:55.000 --> 00:07:00.000
the outside of a building, however they can
also climb internally on the inside of a building.

90
00:07:00.000 --> 00:07:04.000
In this scenario, the weight of the crane
is carried by the constructed portion of the

91
00:07:04.000 --> 00:07:09.000
building, which can increase the lifting capacity
and reduce costs by eliminating the need for

92
00:07:09.000 --> 00:07:10.000
a tall mast.

93
00:07:10.000 --> 00:07:16.000
The process begins in the same way as before
by erecting a crane on top of a concrete foundation,

94
00:07:16.000 --> 00:07:19.000
but the tower must now include a climbing
section at the bottom that will be used to

95
00:07:19.000 --> 00:07:22.000
lift the crane later on.

96
00:07:22.000 --> 00:07:26.000
As the building is constructed around the
mast, two steel collars are installed approximately

97
00:07:26.000 --> 00:07:31.000
three stories apart, which connect the crane
to the building’s structural system.

98
00:07:31.000 --> 00:07:35.000
Climbing rails extend between the collars
down the inside of the open shaft, and these

99
00:07:35.000 --> 00:07:40.000
provide support for a hydraulic jack that
is positioned inside the mast climbing section.

100
00:07:40.000 --> 00:07:44.000
When the crane is ready to be climbed, the
tower is unbolted from the foundation, and

101
00:07:44.000 --> 00:07:48.000
the hydraulic cylinder is pressurized to take
the its weight.

102
00:07:48.000 --> 00:07:52.000
The cylinder is then used to lift the crane
upwards until the bottom of the mast reaches

103
00:07:52.000 --> 00:07:56.000
the first collar, while a ratcheting system
ensures that the crane cannot fall back down

104
00:07:56.000 --> 00:07:58.000
the shaft.

105
00:07:58.000 --> 00:08:03.000
As additional floors are added to the building,
a third collar is installed three stories

106
00:08:03.000 --> 00:08:09.000
above the first two, and the crane can then be lifted from the bottom collar to the middle one.

107
00:08:15.000 --> 00:08:20.000
At this point, the bottom collar is no longer
needed, so it is removed and re-located another

108
00:08:20.000 --> 00:08:26.000
3 stories above, thus allowing the whole process
to be repeated as the building stretches higher.

109
00:08:26.000 --> 00:08:30.000
When construction is finally complete, the
tower crane will either be disassembled using

110
00:08:30.000 --> 00:08:35.000
a larger mobile crane, or a smaller crane
will be hoisted to the top of the building

111
00:08:35.000 --> 00:08:39.000
that can be dismantled by hand once the tower
crane is removed.

112
00:08:39.000 --> 00:08:43.000
Tower cranes play an essential role in countless
construction projects all around the world,

113
00:08:43.000 --> 00:08:48.000
and their ability to climb upwards entirely
on their own means there is virtually no limit

114
00:08:48.000 --> 00:08:49.000
to how high we can build.

115
00:08:49.000 --> 00:08:53.000
These awesome machines always get the job
done safely and efficiently, just like the

116
00:08:53.000 --> 00:08:57.000
sponsor for today’s video, NordPass.

117
00:08:57.000 --> 00:09:00.000
We all know that using a unique password for
every website is the best ways to protect

118
00:09:00.000 --> 00:09:05.000
your online accounts, but it can often be
difficult to remember all these passwords

119
00:09:05.000 --> 00:09:07.000
and time-consuming to type them into webpages
yourself.

120
00:09:07.000 --> 00:09:12.000
That’s where NordPass comes in by storing
your credentials behind a single master password

121
00:09:12.000 --> 00:09:15.000
and auto-filling them online with just one
click.

122
00:09:15.000 --> 00:09:20.000
NordPass was created by the cybersecurity
experts at NordVPN, and it has been carefully

123
00:09:20.000 --> 00:09:25.000
designed to store all your passwords securely
so you can access them from anywhere.

124
00:09:25.000 --> 00:09:30.000
All your data is encrypted locally for maximum
security, and your login details are automatically

125
00:09:30.000 --> 00:09:33.000
backed up and synced between your devices.

126
00:09:33.000 --> 00:09:37.000
Using NordPass has been a huge time saver
for me since I use dozens of online services

127
00:09:37.000 --> 00:09:41.000
daily, and I never have to worry about forgetting
a complex password.

128
00:09:41.000 --> 00:09:45.000
When I signed into YouTube this morning to
publish this video, I simply hit the auto-fill

129
00:09:45.000 --> 00:09:51.000
icon on the right-hand side, selected my saved
login, and my password was filled instantaneously

130
00:09:51.000 --> 00:09:53.000
without ever touching my keyboard.

131
00:09:53.000 --> 00:09:58.000
I have estimated that NordPass can save up
to 10 seconds for every login, and although

132
00:09:58.000 --> 00:10:01.000
that might not sound like a lot at first,
it can easily add up to more than 10 hours

133
00:10:01.000 --> 00:10:03.000
per year.

134
00:10:03.000 --> 00:10:09.000
If you would like to give it a try for yourself,
then simply enter your e-mail address at NordPass.com/ArtofEngineering

135
00:10:09.000 --> 00:10:15.000
to get one month of NordPass Premium for free,
or use code ARTOFENGINEERING10 to get 10%

136
00:10:15.000 --> 00:10:17.000
off a 2-year plan.

137
00:10:17.000 --> 00:10:22.000
NordPass is a powerful tool for keeping your
passwords safe, organized, and accessible,

138
00:10:22.000 --> 00:10:27.000
and I highly recommend that you check you
check them out by going to NordPass.com/ArtofEngineering

139
00:10:27.000 --> 00:10:28.000
using the link in the description.

140
00:10:28.000 --> 00:10:32.000
Don’t forget to subscribe if you enjoyed
today’s video, and remember to hit the bell

141
00:10:32.000 --> 00:10:35.000
to get notified every time a new one comes
out.

142
00:10:35.000 --> 00:10:39.000
If you are interested in supporting Art of
Engineering and future projects, then you

143
00:10:39.000 --> 00:10:42.000
can also check out my Patreon page using the
link below.

144
00:10:42.000 --> 00:10:47.000
As always, thanks so much for watching, and
I’ll see you in the next one.



