00:00:02,350 --> 00:00:07,580
[Music]

2
00:00:04,720 --> 00:00:10,039
no construction site is complete without

3
00:00:07,580 --> 00:00:12,289
its fair share of tower cranes and here

4
00:00:10,039 --> 00:00:14,059
at media city we're no exception

5
00:00:12,289 --> 00:00:17,119
it seems that they appear from nowhere

6
00:00:14,059 --> 00:00:20,810
almost overnight and before you know it

7
00:00:17,119 --> 00:00:23,929
they're in full swing but it's not quite

8
00:00:20,810 --> 00:00:26,329
that easy at this film will show the

9
00:00:23,929 --> 00:00:29,418
team of media city are about to erect TC

10
00:00:26,329 --> 00:00:30,890
10 a saddle jib tower train and we're

11
00:00:29,419 --> 00:00:33,410
going to follow its progress through to

12
00:00:30,890 --> 00:00:34,789
completion first the project manager

13
00:00:33,410 --> 00:00:36,769
with the assistance of the health and

14
00:00:34,789 --> 00:00:37,489
safety support team have to consider a

15
00:00:36,770 --> 00:00:40,730
few things

16
00:00:37,489 --> 00:00:44,989
what type of crane where is it to be

17
00:00:40,730 --> 00:00:47,870
situated how high what length does the

18
00:00:44,989 --> 00:00:50,870
jib need to be what sort of base how's

19
00:00:47,870 --> 00:00:53,510
it going to be built and finally how do

20
00:00:50,870 --> 00:00:56,349
we dismantle the thing something else

21
00:00:53,510 --> 00:00:58,640
that is really important the paperwork

22
00:00:56,350 --> 00:01:00,469
apart from the usual method statements

23
00:00:58,640 --> 00:01:02,329
and permits there are various stages

24
00:01:00,469 --> 00:01:03,559
throughout the crane erection where

25
00:01:02,329 --> 00:01:05,990
checks need to be undertaken

26
00:01:03,559 --> 00:01:09,050
certificates issued and signatures

27
00:01:05,990 --> 00:01:11,240
required so we know where the cranes

28
00:01:09,050 --> 00:01:16,759
going and we know the type of crane we

29
00:01:11,240 --> 00:01:18,649
need but first we need to expose the

30
00:01:16,760 --> 00:01:23,210
piles around which the concrete crane

31
00:01:18,650 --> 00:01:24,620
base will be set the designs are

32
00:01:23,210 --> 00:01:27,350
produced and approved by highly skilled

33
00:01:24,620 --> 00:01:28,640
engineers and enormous care is taken to

34
00:01:27,350 --> 00:01:31,610
make sure that the base is of the

35
00:01:28,640 --> 00:01:35,090
highest standard at last we can start

36
00:01:31,610 --> 00:01:37,160
digging well almost a permit to excavate

37
00:01:35,090 --> 00:01:39,290
must be raised and method statements

38
00:01:37,160 --> 00:01:42,130
produced and discussed with the

39
00:01:39,290 --> 00:01:42,130
excavation team

40
00:01:42,180 --> 00:01:48,210
the site is clear and an exclusion zone

41
00:01:44,580 --> 00:01:50,610
created and although underground utility

42
00:01:48,210 --> 00:01:52,500
checks were carried out previously the

43
00:01:50,610 --> 00:01:55,310
area is scanned with a cat detector

44
00:01:52,500 --> 00:01:55,310
prior to excavation

45
00:02:03,799 --> 00:02:09,050
the important safety word should always

46
00:02:06,109 --> 00:02:17,510
be foremost so guardrails and safe

47
00:02:09,050 --> 00:02:19,610
access routes are put in place piles

48
00:02:17,510 --> 00:02:21,290
down to the correct height blinding

49
00:02:19,610 --> 00:02:22,970
concrete is fought to give us a clean

50
00:02:21,290 --> 00:02:25,269
surface where we can build our steel

51
00:02:22,970 --> 00:02:25,269
cage

52
00:02:37,730 --> 00:02:43,269
these concrete footings are where the

53
00:02:39,920 --> 00:02:43,269
cream-based section will sit

54
00:02:51,990 --> 00:02:56,450
the cage needs to be checked and signed

55
00:02:54,180 --> 00:02:56,450
off

56
00:02:58,240 --> 00:03:10,080
and then preformed walls complete the

57
00:03:01,060 --> 00:03:10,080
structure the base is back filled

58
00:03:11,910 --> 00:03:15,740
and compact it

59
00:03:19,000 --> 00:03:23,050
the first section of the crane which has

60
00:03:20,980 --> 00:03:25,590
been positioned nearby is lifted onto

61
00:03:23,050 --> 00:03:25,590
the footings

62
00:03:29,230 --> 00:03:36,349
the crane base section anchors are tied

63
00:03:31,910 --> 00:03:38,450
into the cage this is pretty critical at

64
00:03:36,349 --> 00:03:40,220
the guys that will erect a must have to

65
00:03:38,450 --> 00:03:45,260
be confident that the base is solid and

66
00:03:40,220 --> 00:03:47,300
safe our temporary works coordinator and

67
00:03:45,260 --> 00:03:50,709
the crane supervisor make the final

68
00:03:47,300 --> 00:03:50,709
checks before the complete is for

69
00:03:53,620 --> 00:03:57,580
give samples percent of the laughs where

70
00:03:56,200 --> 00:03:59,290
tests will be carried out on the

71
00:03:57,580 --> 00:04:01,209
concrete and reports sent to the

72
00:03:59,290 --> 00:04:02,950
temporary works engineer so he knows

73
00:04:01,209 --> 00:04:05,370
when it's safe to proceed to the next

74
00:04:02,950 --> 00:04:05,369
stage

75
00:04:06,230 --> 00:04:10,819
all people weren't completed base

76
00:04:08,810 --> 00:04:12,440
construction thoroughly checked the

77
00:04:10,819 --> 00:04:16,849
project is handed on to the erection

78
00:04:12,440 --> 00:04:18,829
contractor in this case HTC the base has

79
00:04:16,850 --> 00:04:21,019
hardened off and the mast can now be

80
00:04:18,829 --> 00:04:23,060
built after the lifting operations

81
00:04:21,019 --> 00:04:25,580
manager completes his pre erection audit

82
00:04:23,060 --> 00:04:27,260
rated the permit to erect and checks

83
00:04:25,580 --> 00:04:29,120
that the foundation approval certificate

84
00:04:27,260 --> 00:04:31,729
has been issued by the temporary works

85
00:04:29,120 --> 00:04:33,410
engineer the erection team must not

86
00:04:31,729 --> 00:04:36,020
continue without the certificate of

87
00:04:33,410 --> 00:04:37,970
approval we have to extend the original

88
00:04:36,020 --> 00:04:40,460
exclusion zone now that the crane is to

89
00:04:37,970 --> 00:04:42,169
be erected the zone has to take into

90
00:04:40,460 --> 00:04:44,810
account the eventual height of the mast

91
00:04:42,169 --> 00:04:49,549
and the length of the jail this is all

92
00:04:44,810 --> 00:04:51,500
laid out in the method statements we've

93
00:04:49,550 --> 00:04:54,020
allocated an area for the mobile crane

94
00:04:51,500 --> 00:04:57,560
tested the ground and checked insurance

95
00:04:54,020 --> 00:05:00,349
documents this crane is pretty high it's

96
00:04:57,560 --> 00:05:03,790
not going to be freestanding we're going

97
00:05:00,350 --> 00:05:06,290
to tie it into the core for stability

98
00:05:03,790 --> 00:05:07,910
the ties will be fitted to steel

99
00:05:06,290 --> 00:05:10,750
brackets which will have to be fixed

100
00:05:07,910 --> 00:05:13,789
into the core at the required height

101
00:05:10,750 --> 00:05:16,190
would inform us the bunk the location of

102
00:05:13,789 --> 00:05:17,539
the brackets are removed the steel

103
00:05:16,190 --> 00:05:19,990
brackets will have to be checked and

104
00:05:17,539 --> 00:05:22,450
approved by the temporary works engineer

105
00:05:19,990 --> 00:05:26,450
the crane sections are delivered and

106
00:05:22,450 --> 00:05:28,159
inspected by the erection crew careful

107
00:05:26,450 --> 00:05:33,169
attention is paid to the pins and

108
00:05:28,160 --> 00:05:35,180
retaining clips mobile cranes like all

109
00:05:33,169 --> 00:05:37,700
other types of cranes operate under

110
00:05:35,180 --> 00:05:41,470
strict guidelines if the wind is too

111
00:05:37,700 --> 00:05:41,469
strong work starts

112
00:05:49,360 --> 00:05:54,129
as each section is lifted the slinger

113
00:05:52,509 --> 00:05:55,800
banks Minh and operatives on the mast

114
00:05:54,129 --> 00:05:59,650
guide it into place

115
00:05:55,800 --> 00:06:01,180
locate the feet hammer home the pins and

116
00:05:59,650 --> 00:06:05,318
check and confirm that the securing

117
00:06:01,180 --> 00:06:07,000
devices are fixed and in flames the

118
00:06:05,319 --> 00:06:08,620
erection team or though they may have a

119
00:06:07,000 --> 00:06:10,750
head for Heights make sure that

120
00:06:08,620 --> 00:06:13,199
harnesses and safety equipment is one at

121
00:06:10,750 --> 00:06:15,520
all times

122
00:06:13,199 --> 00:06:17,259
now the mast has reached the height

123
00:06:15,520 --> 00:06:19,780
where it is going to be tied into the

124
00:06:17,259 --> 00:06:21,069
core we fixed the yellow tie collar to

125
00:06:19,780 --> 00:06:23,859
the section when it was on the ground

126
00:06:21,069 --> 00:06:27,430
and now we can lift it into its position

127
00:06:23,860 --> 00:06:29,259
on the mast tie legs are assembled to

128
00:06:27,430 --> 00:06:32,889
their approximate length and prepared

129
00:06:29,259 --> 00:06:34,780
for lifting the tour the ties can be

130
00:06:32,889 --> 00:06:36,520
fitted the brackets on the core have

131
00:06:34,780 --> 00:06:39,690
been inspected and approved by the

132
00:06:36,520 --> 00:06:39,690
temporary works engineer

133
00:06:41,470 --> 00:06:46,000
our site engineer checks the tower is

134
00:06:43,780 --> 00:06:47,979
vertical and relates his findings to the

135
00:06:46,000 --> 00:06:51,210
crew so they can make adjustments to the

136
00:06:47,980 --> 00:06:53,680
ties before fully tightening the bolts

137
00:06:51,210 --> 00:06:55,659
now that the tower is tied into the core

138
00:06:53,680 --> 00:07:00,160
we can finish building the mast up to

139
00:06:55,660 --> 00:07:02,650
its final height the a-frame and slue

140
00:07:00,160 --> 00:07:04,630
ring are lifted into place are secured

141
00:07:02,650 --> 00:07:11,799
with high tensile pins and retaining

142
00:07:04,630 --> 00:07:13,810
clips followed by the cab the counter

143
00:07:11,800 --> 00:07:15,610
jib is next being raised off the ground

144
00:07:13,810 --> 00:07:19,300
and changed for balance before being

145
00:07:15,610 --> 00:07:21,490
lifted to the top of the mast a tag line

146
00:07:19,300 --> 00:07:23,170
controls the jib on the way out until

147
00:07:21,490 --> 00:07:27,660
it's placed into its catchment hooks and

148
00:07:23,170 --> 00:07:29,980
secures and the bracing bars attached

149
00:07:27,660 --> 00:07:32,500
the main Jade is assembled in the

150
00:07:29,980 --> 00:07:34,570
exclusion zone trolley ropes and safety

151
00:07:32,500 --> 00:07:36,250
rails are fitted and like the counter

152
00:07:34,570 --> 00:07:40,360
jib it's raised off the ground and

153
00:07:36,250 --> 00:07:42,430
checks for balance the tower crane is

154
00:07:40,360 --> 00:07:46,090
slewed round ready to fit the main gym

155
00:07:42,430 --> 00:07:47,740
which is lifted and secured bracing bars

156
00:07:46,090 --> 00:07:49,960
are connected to the top of the a frame

157
00:07:47,740 --> 00:07:52,990
then the jib lowered to its final

158
00:07:49,960 --> 00:07:54,880
horizontal position all retaining bolts

159
00:07:52,990 --> 00:07:57,840
pins and tie bar connections are

160
00:07:54,880 --> 00:07:57,840
carefully checked

161
00:07:59,449 --> 00:08:06,300
counterweights are lifted into place the

162
00:08:03,930 --> 00:08:08,130
hook block and rope are made ready then

163
00:08:06,300 --> 00:08:09,840
hoist it up to the jib where the fitter

164
00:08:08,130 --> 00:08:13,830
will complete the process and set limits

165
00:08:09,840 --> 00:08:15,539
ready for weight tests before testing

166
00:08:13,830 --> 00:08:17,550
the supervisor will carry out an

167
00:08:15,539 --> 00:08:24,090
inspection including all connections

168
00:08:17,550 --> 00:08:26,669
ballast ropes and Anchorage points the

169
00:08:24,090 --> 00:08:30,060
cranes Bill's a bit more paperwork needs

170
00:08:26,669 --> 00:08:31,919
to be produced the erectors inspection

171
00:08:30,060 --> 00:08:34,200
and handover certificates are issued and

172
00:08:31,919 --> 00:08:37,679
the lifting operations manager completes

173
00:08:34,200 --> 00:08:39,599
his post direction audit before we can

174
00:08:37,679 --> 00:08:42,650
Commission the crane into use there is a

175
00:08:39,599 --> 00:08:42,650
little more work to do

176
00:08:43,059 --> 00:08:51,849
an overload test is carried out so the

177
00:08:48,620 --> 00:08:51,850
crane can be certified

178
00:08:54,160 --> 00:09:00,850
an independent engineer completes a

179
00:08:56,530 --> 00:09:04,990
report of thorough examination and the

180
00:09:00,850 --> 00:09:06,640
management audit is finalized routine

181
00:09:04,990 --> 00:09:08,320
checks will be carried out until the

182
00:09:06,640 --> 00:09:12,400
crane has finished its work and is

183
00:09:08,320 --> 00:09:14,350
finally decommissioned so there we are

184
00:09:12,400 --> 00:09:16,150
a great deal of work and preparation

185
00:09:14,350 --> 00:09:18,730
goes into the erection of the tower

186
00:09:16,150 --> 00:09:21,730
train they don't just appear by magic

187
00:09:18,730 --> 00:09:24,040
and although exclusion zones may seem to

188
00:09:21,730 --> 00:09:24,900
be a real nuisance they are there for a

189
00:09:24,040 --> 00:09:27,400
reason

190
00:09:24,900 --> 00:09:30,310
not to make everyone's life difficult

191
00:09:27,400 --> 00:09:32,280
but to keep everyone safe and out of

192
00:09:30,310 --> 00:09:35,619
harm's way

193
00:09:32,280 --> 00:09:40,439
TC 10 is now fully operating as one of

194
00:09:35,620 --> 00:09:40,440
many tower cranes on the media city site

195
00:09:54,310 --> 00:09:56,369
you
