In this video, we will view the enhancements for a change request (CR) and also for 
a change order (CO).

2
00:00:12,400 --> 00:00:23,633
Let us modify the Change Decomposition field for a CR to Enabled so that we can create a CO manually.

3
00:00:52,933 --> 00:01:02,866
Now, we will promote the CR to the In Process-CO state so that the Create Change 
Order option for CO will be enabled.

4
00:01:36,200 --> 00:01:44,800
Observe that the CR has been promoted to the In Process-CO state after approving the related task.

5
00:01:46,800 --> 00:01:53,300
Let us navigate to the Change Orders page from the category tree.

6
00:02:00,566 --> 00:02:04,932
Observe that Create Change Order option has been enabled.

7
00:02:06,933 --> 00:02:12,366
Let us now create a CO.

8
00:02:30,033 --> 00:02:37,566
We will now select and drag the Change Action (CA) and drop it to CO column to connect the CA to the CO.

9
00:02:56,866 --> 00:03:01,232
Observe that the Decisions and Meetings options have been added to the CO category tree. 

10
00:03:06,833 --> 00:03:11,966
We have seen the enhancements for a CR and a CO.
